California Construction News staff writer
Construction crews are putting the finishing touches on UC Riverside’s new student housing complex project in advance of its opening next month.
Major construction of North District Phase 2 is mostly complete, with work expected to wrap up soon.
The project, which includes 429 apartment-style units and 1,568 new beds, will be completed in just 21 months—a rapid timeline for a development of its size, said Eric Speik, senior project manager for McCarthy Building Companies, the contractor overseeing construction.
Speik credited the fast schedule to the use of prefabricated cold-formed steel wall and floor panels, manufactured and shipped from Mexico, which sped up the construction by about two months.

Final interior work includes carpet installation, furniture setup, window shade placement, and fire alarm testing, Franklin said.
The building’s frontage along Canyon Crest Drive features a two-story pedestrian arcade supported by concrete columns and a shaded roof. A retail space with a market and coffee bar called the Den is expected to open this fall.
Additional amenities include a parking lot, fitness center, laundry room, study spaces, meeting rooms, and two landscaped courtyards.
A ribbon-cutting ceremony is scheduled for Sept. 29.